AI Data Centers in Texas
Huge data centers that power artificial intelligence are being proposed across Texas, and together they have asked to connect several times the grid's record demand. Supporters see investment, construction jobs and a bigger tax base. Critics worry about the grid, water, power bills, tax breaks and noise, and in 2026 the state paused new approvals to audit them.
The basics
A data center is a large building full of computer servers that store data and run software, including artificial intelligence. Nationally, data centers used about 4.4% of U.S. electricity in 2023, and a federal lab projected 6.7% to 12% by 20281.
Texas is one of the busiest markets. As of March 2026, ERCOT was tracking about 410 gigawatts of large loads seeking to connect, about 87% of them data centers3. By August 2026 the state put the figure at about 474 gigawatts, more than five times ERCOT's record peak demand5. ERCOT's record peak is about 91,089 megawatts, set July 22, 2026 (unofficial until final settlement), topping the 2023 record of 85,508 megawatts14.
Many requests may never be built. ERCOT has said its own forecast likely overstates future growth4. Still, lawmakers acted. Senate Bill 6 (2025) set rules for new large customers, 75 megawatts or more unless regulators set a lower threshold. It requires a screening study fee of at least $100,000 and disclosure of on-site backup generators and of similar requests elsewhere in Texas. In grid emergencies, ERCOT can direct large customers that have backup generators to switch to them or cut power use, and large loads connected after 2025 must be able to be curtailed during rotating outages2.
On August 3, 2026, the Governor directed the PUC and ERCOT to audit data center projects in the interconnection process before any more advance, covering tax incentives, power use, on-site generation, water use and ownership5. On September 21, 2026, the Governor ordered the state environmental agency, TCEQ, to pause all permits for data center projects until the audit is done6. ERCOT expects to finish the audit in December 20267.
Water use is another issue. The state water board's 2025 annual water use survey went to 341 data centers, and only 17% responded, even though not responding can be a Class C misdemeanor8. On September 24, 2026, the Texas Attorney General opened an investigation into data center developments that had not responded to the survey, starting with projects in 18 counties including Tarrant and Dallas9.
Key terms
- Large load
- Under SB 6, a single electricity customer using 75 megawatts or more at one site, such as a big data center, unless regulators set a lower threshold2.
- Interconnection queue
- The waiting list of projects asking to connect to the grid. ERCOT is moving to study large loads in batches3.
- Curtailment
- Ordering a customer to cut power use. SB 6 lets ERCOT direct large loads with backup generators to curtail or switch to those generators in an emergency, and requires new large loads to be able to be curtailed during rotating outages2.
- Tax abatement
- A local agreement in which a city, county or special district exempts some of the increase in a property's value from taxes for up to 10 years, usually in exchange for investment or jobs16.
- Qualifying data center exemption
- A state sales tax break for data centers of at least 100,000 square feet that create 20 qualifying jobs and invest at least $200 million over five years10.
In Texas
The Texas Economic Development Corporation, a nonprofit that recruits businesses to Texas, reports that data centers directly employed about 47,856 people in Texas as of mid-2024, about 10% of the U.S. data center workforce17. Texas offers a state sales tax exemption to qualifying data centers, lasting 10 or 15 years depending on investment size10. The state forecast in 2025 that it would forgo $3.2 billion in sales tax over two years11, and the Comptroller's office said that is likely an underestimate. Of 138 certified data centers, only 20 had been audited as of July 2026, and 6 of those were found out of compliance11.
Local decisions matter too. In North Texas, the Fort Worth City Council in March 2026 unanimously tabled a vote on a proposed 50% property tax abatement over 10 years for a $1 billion data center, after hundreds of residents turned out to a public meeting with concerns12. The developer, Edged, withdrew its application on April 30, 2026, before the rescheduled May 12 vote15. Texas counties generally lack the zoning power that cities have, and nearly half of the more than 248 planned Texas data centers are slated for unincorporated areas outside city limits13. In Hood County, southwest of Fort Worth, eight data centers have been proposed across more than 7,600 acres13.
The August pause applied only to projects of 75 megawatts or more inside ERCOT, so smaller data centers, projects with their own power, and areas outside ERCOT were not covered7. The September permit pause reached more projects7. Some critics have urged a special legislative session before the regular session begins in January 20277.
How people see it
The strongest case for each view, in terms its supporters would recognize. We don't pick a side.
Welcome the investment
Data centers bring billions of dollars in investment, thousands of construction jobs and a much bigger local tax base that can lower taxes for everyone else. Texas competes with other states for this industry, and incentives help win it. Texas already added safeguards in SB 6, such as study fees and emergency power cuts for large users, so new rules should not drive the industry to other states2.
Growth if they pay their own way
Data centers are welcome, but they should cover the full cost of the power lines and plants built for them, bring or pay for their own water and backup power, and not raise bills for households. Clear state rules, like SB 6, can protect the grid while keeping Texas open for business.
Local control and limits
Neighbors live with the noise, traffic, water draw and land use, so local communities should have a real say. Counties need tools to set rules on siting, noise and water, and tax breaks should be reconsidered when permanent jobs are few.
Pause until we know more
The state does not yet know how much water many data centers use, and requests far exceed the power Texas can supply. New approvals and tax breaks should stop until audits show the grid and water supply can handle them.
Stop new large data centers
The water, land, grid strain and neighborhood impacts are too large for the relatively few permanent jobs these facilities create. The state should stop approving new large data centers and end their sales tax break, which already costs billions of dollars in forgone revenue11.
Who decides
- Texas Legislature and Governor: Write grid, water and tax laws, including SB 6 and the data center sales tax exemption. The Governor issued the 2026 audit and permit pause256.
- Public Utility Commission and ERCOT: Set and apply rules for connecting large loads to the grid and are running the 2026 audit25.
- TCEQ (state environmental agency): Issues air and water permits, such as for on-site power plants and water rights, and was ordered in September 2026 to pause data center permits67.
- Texas Water Development Board: Surveys water use and plans for the state's water supply89.
- Texas Comptroller (elected): Certifies and audits data centers that get the state sales tax exemption1011.
- City Council and County Commissioners Court: Decide local tax abatements. Cities also control zoning, which counties generally lack1213.
- Attorney General (elected): Enforces state reporting laws, such as water use surveys9.
Questions to ask a candidate
- Should Texas keep, limit or end the sales tax exemption for data centers?
- Who should pay for new power lines and plants built to serve data centers?
- Should counties get zoning power to decide where data centers go?
- Should the state require data centers to report their water and power use publicly?
Last reviewed 2026-09-26. Spotted something wrong? Every claim links to its source so you can check it yourself.
Sources
- DOE Releases New Report Evaluating Increase in Electricity Demand from Data CentersU.S. Department of Energy
- Senate Bill 6, 89th Legislature (enrolled text)Texas Legislature Online
- ERCOT Update to the Senate Committee on Business and Commerce, April 1, 2026ERCOT
- ERCOT Releases Preliminary Long-Term Load Forecast for Years 2026 to 2032ERCOT
- Governor Directs Comprehensive Data Center Audit (Aug. 3, 2026)Office of the Texas Governor
- Governor Directs TCEQ To Halt Data Center Permits (Sept. 21, 2026)Office of the Texas Governor
- Gov. Abbott orders TCEQ to pause environmental permits for data centers until audit is completeKERA News
- Texas asked data centers to report water use. Most didn't respondKUT News
- Attorney General Launches Investigation into Data Center Developments Over Water Use Reporting (Sept. 24, 2026)Office of the Texas Attorney General
- Texas Tax Code Section 151.359: Property Used in Certain Data CentersTexas Public Law
- Texas' multibillion-dollar sales tax exemption for data centers is growing, while audits lagKXXV / The Texas Tribune
- Enough concern today: $1B data center stalls; city, residents raise questions about tax breakFort Worth Report
- Eight data centers threaten to transform this small Texas county. Local officials say they have no power to stop them.KBTX / The Texas Tribune
- ERCOT Peak Demand RecordsERCOT
- Proposed Veale Ranch data center withdraws request for Fort Worth tax break (May 6, 2026)Fort Worth Star-Telegram (via Yahoo News)
- Chapter 312 Tax AbatementsTexas Comptroller of Public Accounts
- How Data Centers Benefit Texas CommunitiesTexas Economic Development Corporation